Turning Groundwater Surprises into Solutions at Science Centre Station

Construction worker at a groundwater site | Science Centre Station

Project overview

Construction worker at a groundwater site | Science Centre Station

The Eglinton Crosstown LRT is Canada’s largest transit expansion. It is a high-profile project where delays carry real cost for the city and its residents. When construction teams uncovered unexpected groundwater at Science Centre Station, progress came to a sudden halt. The site had been assessed as dry, but the reality underground told a different story.

One morning, WJ Canada received an urgent call from the CTS team at Science Centre Station. Groundwater had appeared at the bottom of the excavation, halting progress. At 800 metres long, Science Centre is the largest and deepest excavation on the Eglinton Crosstown project, with its lowest point running beneath Don Mills Road. A fast, engineered response was critical.

Location

Science Centre Station, Eglinton Crosstown Light Rail Transit

Client

Crosslinx Transit Solutions

Main contractor

CTS

The Challenge: Groundwater Where None Was Expected

A previous hydrogeological report indicated that no groundwater would be present. But as the CTS crew reached the base of the excavation, they encountered nearly one metre of water sitting above the clay till. The unexpected inflow stalled the final stages of excavation and delayed the start of concrete placement. Without a fast solution, the project faced significant disruption.

Our Response: Rapid Deployment and Engineered Precision

Within days of receiving the call, WJ Canada mobilised to site and began work immediately. Our team designed and installed a system of inclined wellpoints on both the north and south sides of the excavation. Drilling was carried out from the base of the shaft, through the lagging wall, allowing us to commission the system efficiently and without delay.

Results: Groundwater Controlled, Schedule Recovered

Within two weeks of the initial call, WJ Canada successfully dewatered the Station site. CTS resumed excavation in dry and stable conditions. Three months later, all concrete and waterproofing work was complete, and WJ safely decommissioned the system. The project was back on track with minimal disruption.

WJ came in on very short notice and executed a professional and effective dewatering solution. Their solution was cost effective and efficient as the wells were short and installed from the base of the excavation. The solution was tailored to our needs as they allowed us to complete our station build-back all the while remaining functional behind the waterproofing membrane. I would recommend WJ to any contractor in need of a dewatering partner.”

Diego Ocampo, Project Manager, Science Centre

Engineering Certainty When It Matters Most

Unexpected groundwater can derail even the most carefully planned projects. WJ Canada responded with speed, precision, and a solution tailored to complex site conditions. Our team worked closely with CTS to restore control below ground so progress could continue above it.

This project is one of many where WJ’s engineering-led approach, deep technical expertise, and commitment to partnership have helped keep major infrastructure moving forward. When the unexpected happens, we bring clarity, confidence, and control.

Other projects

WJ have completed many projects in Canada and globally. Click on the links below to learn more about what we do.

Contact WJ Canada

Are you ready to see what else our vision can bring to your projects? Why not speak to our team of groundwater experts today?